Capital work-in-progress ageing (` cr) Particulars As at March 31, 2025 As at March 31, 2024 Less than 1 year 1-2 years 2-3 years More than 3 years Total Less than 1 year 1-2 years 2-3 years More than 3 years Total Projects in progress 88.12 14.75 15.21 6.25 124.33 184.50 83.24 9.87 3.14 280.75 Projects temporarily suspended - - - - - - - - - - Capital work-in-progress (projects in progress) whose completion is overdue (` cr) Particulars As at March 31, 2025 As at March 31, 2024 Less than 1 year 1-2 years 2-3 years More than 3 years Less than 1 year 1-2 years 2-3 years More than 3 years Project 1 - - - - 16.00 - - - Project 2 - - - - 1.00 - - - Project 3 5.00 - - - 45.00 - - - Project 4 - - - - 4.00 - - - Project 5 2.00 - - - 72.00 - - - Project 6 - - - - 9.00 - - - Project 7 4.06 0.12 0.27 - 2.82 0.74 0.25 - Project 8 21.55 - - - - - - - 32.61 0.12 0.27 - 149.82 0.74 0.25 - 254 254 Integrated Annual Report 2024-25